SAIYU - Invoicing to Clients

Date: 09.02.2025 | Revision: 2025.02.a

Overview

Starting from 2025, all invoices from Saiyu will be managed exclusively through Buildertrend, regardless of the contract type. The invoicing pipeline is scenario-based, tailored to the nature of the contract. The following sections outline the pipelines for each contract type:

  • Lump Sum Contract
  • Design and Construct (D&C) Contract
  • Cost Plus Contract

More reading about Contract Types

Flow Chart

1. Lump Sum Contract

Description

A fixed-price contract with a clearly defined scope of work. Invoicing is straightforward, issued as progress claims or at predetermined stages.

Process

  1. Invoice Generation

    • Generate the client invoice (progress claim or per stage) directly from Buildertrend.
  2. Financial Disclosure

    • No internal financial details from Saiyu are disclosed in the client invoice.
  3. Synchronization to Xero

    • Sync the generated client invoice from Buildertrend to Xero.
  4. Final Issuance

    • Issue the final invoice to the client from Xero.

2. Design and Construct (DNC) Contract

Description

In this contract, the contractor is responsible for both design and construction. Depending on client requirements, partial financial information may be disclosed.

Process

  1. Review POs

    • Review Purchase Orders (POs) in Buildertrend.
  2. Invoice Generation

    • Convert the POs into a client invoice in Buildertrend, incorporating any contract required partial financial disclosures.
  3. Consultant Handling

    • All consultants involved are treated as subcontractors within the invoicing process.
  4. Synchronization to Xero

    • Sync the generated client invoice from Buildertrend to Xero.
  5. Final Issuance

    • Issue the final invoice to the client from Xero.

3. Cost Plus Contract

Description

A contract where the owner pays actual costs (labor, materials, etc.) plus an agreed fee. This is the most complex scenario and is split into two pipelines:

  • One for Saiyu’s management services
  • Another for the construction component

3.1 Management Component

Process

  1. Timesheet Recording

    • Record all management activities via timesheets in Buildertrend.
  2. Invoice Generation

    • Generate a management invoice directly from the timesheets in Buildertrend.
  3. Synchronization to Xero

    • Sync the generated client invoice from Buildertrend to Xero.
  4. Final Issuance

    • Issue the final invoice to the client from Xero.

3.2 Construction Component

Process

  1. PO Creation

    • Create a Purchase Order (PO) in Buildertrend for construction activities.
  2. Invoice Generation

    • Convert the POs into a client invoice in Buildertrend.
  3. Synchronization to Xero

    • Sync the generated client invoice from Buildertrend to Xero.
  4. Final Issuance

    • Issue the final invoice to the client from Xero.

Summary

  • Unified Platform

    • All client invoices are managed through Buildertrend and synchronized with Xero.
  • Lump Sum Contracts

    • Invoices are issued as progress claims or at predetermined stages.
    • No internal financial data is disclosed to the client.
  • Design and Construct (DNC) Contracts

    • Invoices may include partial financial disclosures as required by the client.
    • Consultants are treated as subcontractors.
  • Cost Plus Contracts

    • Management Invoicing
      • Generated from timesheets in Buildertrend, synced to Xero, and issued to the client.
    • Construction Invoicing
      • Generated from a Purchase Order in Buildertrend, synced to Xero, and issued to the client.